Capital Line Items

Visuals in this post: Capital Line Items Line Items by Project Labor by Trade Parts and Supplies Cost per Building Most Expensive Buildings Repairs by Year
Budget October 2026

Where planned restroom capital goes

Construction is 72% of planned restroom capital; design and supervision take a quarter

Planned commitments for 52 Parks restroom projects, $153.6M in total, by line item. Parks’ in-house design and supervision (IFA lines) come to 20%, outside design and supervision another 5%.

  • Construction
  • Design
  • Supervision
  • Other and services
Source: NYC Capital Projects Database, Commitments (djxg-kcfi) and Projects (fi59-268w), FY2026 Adopted Capital Commitment Plan, NYC Open Data Note: Planned future commitments, not spending to date. Excludes the $150.4M “Citywide Public Restroom Buildings” pool, which is not yet assigned to sites.

What IFA means: Inter-Fund Agreement lines pay Parks’ own design and inspection staff out of capital funds. Other: $3.3M for the design phase of a new park and restroom at Nameoke Avenue, recorded without a type.

How restroom buildings were identified: 696 buildings in Parks’ asset system whose description names a public restroom, comfort station or bathroom. Data pulled: October 16, 2026, from the NYC Open Data API. Construction totals by project: the NYC Parks Capital Project Tracker lists 23 completed single-site new restroom buildings with a median total of $3.865M.