← Streets Plan 2026

Fiscal Impact

Tables in this post: Overview Compliance Tracker Fiscal Impact Program Breakdown LL195 Mandates

10-Year Fiscal Impact by Plan Period

All figures represent additional costs above the existing DOT baseline, they are the marginal legislative cost of LL195 mandates, not the full DOT program budget. Figures are from the NYC Council Finance Division's official fiscal impact statement (Oct 2019).

Cost category FY22 (year 1) Plan 1: FY22–26 Plan 2: FY27–31 10-year total
Expense costs $53,506,828 $376,725,018 $367,425,418 $744,150,435
Capital costs $61,017,147 $251,612,715 $545,484,480 $997,097,195
Revenue impact $0 $0 $0 $0
Net fiscal impact $114,523,975 $628,337,733 $912,909,898 $1,741,247,630

Costs are additional above DOT's existing budget baseline; they are not total program costs. Source: NYC Council Finance Division, Fiscal Impact Statement for Proposed Intro. No. 1557-A, Oct 25, 2019.

About this data

  • Fiscal figures are "additional above baseline." The fiscal impact statement estimates the marginal cost of LL195 mandates, what NYC must spend beyond existing DOT commitments. They do not represent total DOT program budgets. For example, DOT had already committed to $59.2M/yr for 50 miles of bike lanes; the $11.8M figure in the program breakdown is only the additional cost above that.
  • Fiscal impact statement date: October 25, 2019, prepared before the law took effect. Actual costs may differ from estimates as scope, inflation, and DOT priorities have changed since.
  • Revenue impact is $0 across all periods. LL195 imposes no new fees or charges.
  • Source code and raw CSV files are available on GitHub.